Re: Work Center and Work Center Category.

$
0
0

Hello Yash,

 

In the screen CR01 (Menu/ Logistics/Production/master data/ work center/ create) see the list of Categories appearing. and study in SPRO (Production/Basic Data/Work Center/General Data/define work center category) the commonality of these Categories by going into Application.

Capture.JPG

 

You would find one thing common here: i.e.,P - Routings for Production

Capture.JPG

 

So, when you give this value in Application to your Category, then it will be appearing there in the list of CR01.

 

Similarly the entry I (Maintenance Tasklists) in Application would make the Category appear in Tcode IR01. (Plant Maintenance > Environment > Work Centers > IR01 - Create ).

 

 

Good luck

KJogeswaraRao


 



Re: IBIP TOOL

$
0
0

Hi Sine ,

 

Please define new Logical File and Logical Path and try again ,See exemple here

screenshot_Thu_Jun_18_15.47.23.png

screenshot_Thu_Jun_18_15.51.24.png

screenshot_Thu_Jun_18_15.53.16.png

screenshot_Thu_Jun_18_15.53.37.png

screenshot_Thu_Jun_18_15.54.26.png

screenshot_Thu_Jun_18_15.54.52.png

screenshot_Thu_Jun_18_15.55.26.png

 

screenshot_Thu_Jun_18_15.56.12.png

 

 

screenshot_Thu_Jun_18_15.57.47.png

 

screenshot_Thu_Jun_18_16.03.24.png

      Fill Logical file : Z_IBIPTOOL_LOGICAL_FILE

screenshot_Thu_Jun_18_16.06.33.png

screenshot_Thu_Jun_18_16.09.30.png

Good Luck

Regards,

Ziv

Re: Maintenance order error

$
0
0

Hi Lokesh,

 

Responsible cost center in work order (Additional data tab) is derived from the cost center maintained in the MainWork Ctr defined in the Header Data tab of maintenance order.

Profit center (Additional data tab) is derived from the profit center maintained in the responsible cost center master data.

 

Responsible cost center: Go to IR03 > Costing tab> refer to 'Cost center field'

Profit center: Go to KS03> put responsible cost center > go to basic data tab > refer to 'Profit center' field

 

Hope this helps!

 

Thanks,

Tajinder

Re: Maintenance order error

$
0
0

This is standard SAP behaviour. If you are not getting values as defined above, there will be some enhancements done by the finance team. Get in touch with your finance counterparts in that case.

 

Thanks,

Tajinder

Re: Regarding construction types

$
0
0
Sai Mohan,

 

What about IE05?

 

PeteA

Re: Detection Catalog Profile

Activities created by Bapi, they are not transferred to MRS

$
0
0

Hi Experts!..

 

I thank them can help me solve a problem we're having in MRS,

I'm trying to integrate non-SAP external system via an RFC to PS, such integration creates activities within the graph currently in SAP ERP is active MRS.

MRS through demand generated is planned from PS activities.
user status is set to create the OK02 transaction activity, scheme: RMFS0001 text: user status, status: STPL, Initial status: X

For this, I am using the bapi: BAPI_BUS2002_ACT_CREATE_MULTI

when designing the RFC program I consider the following
calls to the following additional documentation according BAPIs that are required for the appropriate performance:

1. BAPI_PS_INITIALIZATION
2. BAPI_BUS2002_ACT_CREATE_MULTI
3. BAPI_PS_PRECOMMIT
4. BAPI_TRANSACTION_COMMIT


The problem is that when running the RFC PS activities are created, but these do not happen as demand MRS.
They have any idea why the demands are not transferred to the MRS planner.

 

Thank´s

Regards

 

Damy Vidal

Re: Detection Catalog Profile

$
0
0

Thank you Pete. I may not be able to get through that link because I do not have any ID and password to access. I'll keep searching for information.

Regards.


Re: Regarding data extraction from table

$
0
0

Hi Prashantha,

 

I think you are putting some value in field WERK (Plant) in table EQUI and then expecting to get the results for that plant. Unfortunately WERK in EQUI table is not the right field to use to extract plant specific data for equipment master.

 

Now you can filter the equipment using below 2 criteria:

1) If you want to filter equipment using Planning Plant, put value of planning plant (field IWERK) in table EQUZ

2) If you want to filter equipment using Maintenance Plant, put value of maint plant (field SWERK) in table ITOB

 

Hope this helps!

 

Thanks,

Tajinder

Using surcharge percentage in Purchase Requisition

$
0
0

Is there a way to enter a surcharge as a percentage of the total value of the line above in a purchase requisition?

 

A picture is worth a 1000 words, so here we go:

In the attached snip, we purchased 24,000 kg of blasting powder. We are charged two surcharges, a % on the total value of the powder. Is there a way to enter it into this form?

What we have been doing is just calculating it out and entering a quantity of 1; unit of Each; Price is the calculated price - say $504.

This does not seem to me to be the proper way of entering it, and if the quantity of powder were to be changed, then the surcharges would have to be re-calculated.

 

If someone knows of a better way, feel free to share:-)

 

Thanks in advance.

Re: Send email when call object created from Maintenance Plan

$
0
0

Hi Pete,

 

Thank you for your edit report doc. The reason the user want to send email because a group of people want to know there are preventive work to be done today.

 

The email is like daily send to a group stating list of preventive work order that are due on the current day.

 

 

Hope it clarify.

 

Regards

equipement transfer

$
0
0

Hello dear experts,

 

- Supposing that we have two production units A and B. We are using an equipement X in A and we want to transfer it to B. How can we proceed to do that and what are the changes that have to be made ??

- To do that are we supposed to modify the informations related to the equipement or there a transaction or another way to do it since we have a historical data of use f this equipement ??

 

Regards.

Re: Is there any way to change early start date on WO without going into the operations date tab?

$
0
0

Hi Terry,

 

At our site we have a lot of people making work orders for the equipment all differently making it a planners headache to fix.

if you are talking about order created redundantly/duplicate then better activate object info Pop up, which intern will give information to user that there are some open orders against this Equipment.

 

it is more of a training user or else you should think of having some custom/enhancement logic to Pop up and restrict user from creating duplicate Order.

 

Rgds

Sunil

Re: equipement transfer

Re: Task List type E in Planning Tab of PM Order

$
0
0

REKHA,

With that explanation, this discussion does not stop there and does not answer fully the 'why?'. Because the why will arise again when this field will be  overwritten by some tasklist details, then it will not be necessarily 'E'. Now we need to explain the PRT logic after this over-writing, which happens almost in 100% of the Orders. In other-words, the significance of 'E' to be explained keeping in view its very temporary existence.

 

 

KJogeswaraRao


IP20 - Maintenance Plan Number Range - Assigning Old Numbers

$
0
0

Hello Experts

 

I am hoping one of you, may be able to provide some information in regards to the assignment of new maintenance plan numbers.

We have a scenario were an old maintenance plan number (not previously used) was assigned. This is for internal numbering only.

My understanding is we have buffering in use, which can cause a gap in the number assignment.

I would have expected the sequencing to only move forward in numbers not backwards. Is this part of the standard design or an error?

 

Any help you could provide would be appreciated. I had done some manual searching to see if any other discussions included the same scenario, but was only able to find one related to purchase requisitions that mentioned applying a note and changing the settings to remove buffering.

 

SNRO - MPLA_NR.jpg

 

Our last maintenance plan created according to number was on Apr 30, 2015 and is number 275

Our last maintenance plan created according to date was on Jun 18, 2015 and is number 242

We starting using the maintenance plans originally on Mar 5, 2013, creating plan #1.

This is the first time a old number has been assigned by the system.

 

Maintenance Plans 1-275.jpg

 

Thanks, Sarah

Re: IP20 - Maintenance Plan Number Range - Assigning Old Numbers

$
0
0

Hello Sarah,

 

Your situation (number allotment FORWARD and BACKWARD) is quite NORMAL. It happens everywhere and with many SAP objects. This is a phenomenon with Production client because there will be many servers here. It is not the case with clients with single server like Dev, Quality or others. Buffering is arranged for reducing response times. For example if you set the Buffering to 1, the response times for creating a number will be too much.

 

 

 

Regards

KJogeswaraRao

Re: IP20 - Maintenance Plan Number Range - Assigning Old Numbers

$
0
0

I am attaching today's example in my server. The Notification numbers are in the Descending order of Time. If you observe carefully, at the arrow points the Notification numbers moved backward. Here also the buffer is 10. In maintenance Orders the buffer is 20. These are standard recommended settings and the expected behavior too.

Capture.JPG

 

 

Regards

KJogeswaraRao

Re: IP20 - Maintenance Plan Number Range - Assigning Old Numbers

$
0
0

OK Thanks Jogeswara! This is very helpful. I will let my end users know

Re: Is there any way to change early start date on WO without going into the operations date tab?

$
0
0

How can you activate the object info pop-up? I know how to do a lot of the variants, and am trying to get everyone on the same page.