Re: Tasklists selection via order not working
Greetings Peter, Actually, I believe that the status 4 includes 2 for the purposed of this election. Therefore any Task List that is in status 4 - "Generally released" should be picked up by the...
View ArticleRe: Problem in IP30 call schedule program
Hi, Previous measuring document updated in 01.03.2013.. Counter reading was = 582327
View ArticleProblem in IP30 call schedule program
Hi Mahesh, Cycle plan : 60000 each Call horizon = 100% Scheduling period = 5 yrs Previous measuring doc generated on = 01.03.2013 counter reasding was = 582327 Please let me know if you need any...
View ArticleRe: Partner functions in Maint Notification
HI,Maheswaran i am closing thread Regards,Kumar
View ArticleRe: InResponsibilities subscreen can i have user id
Hi,MaheswaranWill you guide me how to insert both user responsible and user responsible fields in the Responsibilities sub screen of Notification header Tab?Please give the complete Navigation of...
View ArticleRe: InResponsibilities subscreen can i have user id
User response and Person responsible fields?
View ArticleRe: Problem in IP30 call schedule program
As per your screen shot, call is still on Hold status only. Call has not been generated. Once the counter reading reaches the multiple of your Maintenance plan cycle, then call will be generated, if...
View ArticleRe: InResponsibilities subscreen can i have user id
For Partner function definition ---- IMG - PM & CS - Maintenance & Service Processing - Maintenance & Service Notifications - Notification Creation - Partners For Screen Templates --- IMG -...
View ArticleRe: doubt regarding change in cost center in maintenance order
If Reservation has been created against order, where do you want to change the Cost center?? Only while settlement, cost will be settled to cost center, if cost center has been assigned as settlement...
View ArticleRe: MTBF through MCI7 with EQ/FLs
If you give both Functional Location & Equipment, then system will check for the data with the given combination. If no orders or no data available with that Functional Location & Equipment...
View ArticleRe: how to change the company code in ie02
As per SAP PM Enterprise structure, for the new company code, you will be defining new Maintenance Plant. So change the Maintenance Plant in Location tab so that Company code will be changed...
View ArticleRe: MTBF through MCI7 with EQ/FLs
Jitendra, Try running the MCI7 report by putting in the Equipment no. under the Selection Options. The report runs and shows you the MTTR/MTBR for that particular Equipment. Then use the "Switch...
View ArticleAssignment of network activities into PM order.(PM/PS)
Hi Guys, My client wants assignment of network activities (which are created in PS) into PM order.Can any one let me know in detail how to do? In ideal scenario what will be the business benifits?...
View ArticleRe: Assignment of network activities into PM order.(PM/PS)
WBS Elements will be drilled down into network activities. Each network activity will be created as one PM Order. There are some pre-requisites required for this integration. Below link may be useful...
View ArticleWhich to choose SAP PP or SAP PS
Hi,I'm certified in SAP PM and i am newbie in consulting with just 6months exp, i have 5 yrs in Plant maintenance domain. Currently i have been asked to work in SAP PS or SAP PP, could you please...
View ArticleRe: Which to choose SAP PP or SAP PS
Both are having its own pros & cons. Still I would suggest you to go for SAP PP as you have domain experience in SAP PM. I hope, that domain part is in Manufacturing Industry. If so, opt for SAP PP.
View ArticlePRT Availability Check in Work Orders is not working
Dear Experts,I have created Equipment PRT and then I set them in Task List. For testing, I created 2 work orders scheduled at the same time with the same operations and with the same PRT, but when I...
View ArticleMass change of Master warranty field in Equipment master
Hi SAP Gurus, I would like to know if there is a way for mass change of Master warranty field for many equipments in one transaction I have explored two options Option 1 : Use LSMW or BDC which we are...
View ArticleRe: PRT Availability Check in Work Orders is not working
For Equipment PRT, Availability check will not work. You have to do some custom development. Also many threads available for this topic. Please search in forum.
View Articlehow the defective material stock updation will occur after remove from the...
Dear PM Guru, I have one scenario, in my company, my motors and some of the belts will be repaired and after that again they will use these repaired materials. When they issue the new material that...
View Article