Re: Maintenance strategy changes resulting in wrong planned date

$
0
0

Hi Arifulla,

 

Replication is simple. As per standard SAP, below is what it will calculate

 

Source : SAP help

 

Previously used maintenance package: 3M (every 3 months)
New, replacement maintenance package: 4M (every 4 months)

 

The next maintenance task is due for the first time after one month (This is why your next call is showing after 1 year), because the 3 month package has already been called up at least once. If you want to ensure that the next task is actually due after 4 months, then you must restart the maintenance plan.

 

I have given incorrect info in my earlier about the second planned date.

 

Regards

Terence