Re: In IW32 not able to see Cost in USD when PM order status is CRTD
Hi, Actually Cost will be determined when the status is CRTD, if it not determined then check system status CRTD I0001 in BS23 whether RKME - Determine cost is allowed or not? regards,santosh
View ArticleRe: Equipment record sub-assembly with PO creation
Each time you purchase same Packed Equipment, sub equipment can be different. I hope, it won't same in all cases either with same vendor or different vendor. Then, for every PO, in which you buy that...
View ArticleRe: In IW32 not able to see Cost in USD when PM order status is CRTD
Hi Vishu,To my knowledge, as per the standard maintenance order configuration, the Cost computations in Cost tab happen only after REL status. Jogeswara Rao K
View ArticleRe: WBS Element linked to Asset not appearing in Purchase Requistion
Also such assets are called AUC type assets. You can gather more information in this keyword.CJ20n will resolve the WBS release issue
View ArticleRe: Issuance of fuel to equipment from Project Stock
That's not the problem sourabh ... the problem is the type of stock at the gas station. Besides, there are a number of projects running and if we keep opening a new gas station for every project that...
View ArticleRe: Refurbishment Orders are Not Supported
Hi Santosh, As u mentioned in ur previous reply, The process will be once the service material with Item category IRRS triggers, system should trigger automatically IRRE which will allow you to do...
View ArticleRe: Defining new Value Category for Material Cost
Information System reports are analysis reports where in all different cost can be displayed. Seeing cost at order level is detailed one which lower hierarchy people will be interested. For higher...
View ArticleRe: Defining new Value Category for Material Cost
Report requirements of such nature can easily be developed, if the FS (functional specifications) are explained to an ABAPer. Not exactly this we have developed several such reports in Orders area,...
View ArticleRe: Refurbishment Orders are Not Supported
Hi, in the transaction code VORP, check whether you have the settings as similar to below screenshot make the settings and try to processand this repair process under the item category IRRS and try...
View ArticleRe: Defining new Value Category for Material Cost
Hello Maheswaran, Thank you for the update. Has anyone else worked on a similar requirement? Request your help. RegardsSeenu
View ArticleRe: In IW32 not able to see Cost in USD when PM order status is CRTD
Hi All, Thanks for your responce. Our problem is we can see the cost in EUR but not able to see in USD (even select USD radio button)with same T code IW32 when order status is CRTD.But when we release...
View ArticleRe: Work Centre wise report
If you want to get the list based on work center, assign that in notification, orders & operations. Total Notification Raised - IW29Total Order created - IW39 / IW49NTotal Order Confirmed - IW39 /...
View ArticleRe: ME51N - Field Operation Maintenance Order
Thank you,saved mylife withthis answer. Adilson
View ArticleIW29 - Notification report error
Hi All, While I am executing IW29 display notification,, the report shows different times in completion of time and reference time field/time of change .For Eg: completion time : 12:55...
View ArticleRe: Work Centre wise report
Thanks Mr. Maheswaran, I want a single consolidated report, can you please guide me how to create custom report.
View ArticleRe: Control power off (work permit)
Permits at Maintenance Order is possible only at header level. Please provide your requirement in detail, so that some other option can be used here.
View ArticleRe: IW29 - Notification report error
Completion time is different with Reference time. Time of change will reflect last change done on notification. Reference time is manual entry to capture the time by which this notification would have...
View ArticleRe: Work Centre wise report
For Notifications, refer QMEL - ARBPL field for work center. Based on that field & Created on value (QMEL - ERDAT), you can get the no. of notifications. For Orders, work center can be assigned at...
View ArticleReparir order Quantity doubt
Hi Experts When I'm creating a repair order (RAS) from notification IW51, I'm having the following concerns. 1) If I take the Material Quantity say 5 & the serviceable quantity 5 too than its...
View ArticleRe: Work Centre wise report
Hi Kamlesh,It is natural that such report requirements arise as per the client practices and needs.Very often we do not find ready answers in the form of standard programs(Tcodes). For such situations...