Re: how to correct a wrongly inputed counter reading
Hello, Enter the measuring document number in IK12 & follow the process as mentioned in screen shot. This is only the process.If you get some message for refusal then paste the screen shot.
View ArticleRe: Maintenance Plan for a year with Technician Name
You could run IP24 by equipment number, functional location, maintenance plan, main work center, task list, etc. You could then change the output layout to include start date, functional location,...
View ArticleRe: Maintenance Plan for a year with Technician Name
Despite the risks in this planning too long + focus in person (turnover?), the solution is you make each employee be one Work Center.
View ArticleRe: Reserve a set of equipment numbers for projects
Thanks I will try this... Thanks you all for your help.
View ArticleRe: Maintenance Order has stopped generating from Maintenance Plan
Dear Pete, Kindly refer to the screen shot below. One additional question why it stopped on 25 April 2013 as shown in the previous screen. This is not the right case. Since today is 26 April...
View ArticleRe: Confirmation - Possible to use codes for a confirmation?
You could always configure a reason code for variances on the confirmation (IW41). This will allow you to put A, B, C, or D when you confirm each operation step. You can also put additional comments in...
View ArticleAssignment of default settlement rules to multiple maintenance orders
Hi, Can someone advise me on the best way to assign the settlement rule for multiple maintenance orders based on the default settlement profile. Our client wants to change the timing of settlement rule...
View ArticleRe: Confirmation - Possible to use codes for a confirmation?
I assume that you haven´t interest in issues about maintenance history (only in quantity man-hour and the activity done). Therefore Sebastian Lenartowicz solution´s the best option. Remember, there are...
View ArticleRe: Service order creation by PM order
Check the configuration under PM & CS - Maintenance & Service Processing - Maintenance & Service Orders - Functions & Settings - Define Change Documents, Collective Purchase...
View ArticleRe: Multilevel approval for Permit
Hello, Have you checked the options which have been given???
View ArticleRe: Background job processing RISTRA20 -PM maintennace plans
If you run first time, system will take 7 days. If you run on 2nd day, system will consider 2nd day to 8th day (7 days). If any changes have been made in maintenance plan, rescheduling will happen...
View ArticleRe: Reserve a set of equipment numbers for projects
But every time changing the Number range configuration will not be correct solution.
View ArticleRe: Maintenance plan scheduling (Change of frequecy for one item)
If its strategy based plan, then remove one month operation tick box in Maintenance Packages of Task list. If its single cycle plan, then you have to go for separate plan. As per your initial details,...
View ArticleRe: External Number Ranges
You can define your own number number range with Alphanumeric characters. Click Create New button & define the new number range as per your requirement.
View ArticleRe: Assignment of default settlement rules to multiple maintenance orders
Once you release the order, you can't revoke that Release. So, you can use LSMW to upload the settlement rule. For the future orders, system will take default rule as per settlement profile.
View ArticleRe: Maintenance plan scheduling (Change of frequecy for one item)
Hi Mr maheshwaran, Thanks for your reply,I have tried to do the same, created one maintenance plan (With Strategy), and after saving maintenance plan i have removed the one moth pacakage from task list...
View ArticleRe: Maintenance plan scheduling (Change of frequecy for one item)
If you have a single task to be performed only once, and it doesn't fit into the normal cycles then you can either create a separate plan, or manually create the order up-front. Another option is to...
View ArticleRe: Run time Error for IW31 and IW21
Hi YogeshPlease find the screen shot Regards,Keerthan
View ArticleRe: Run time Error for IW31 and IW21
It looks like you have some bad code in user-exit IWO10009 (at order SAVE event). Get your ABAP team to take a look at program ZXWOCU07 PeteA
View Article