Re: Once-only cost posting for labour
Instead of using activity rates to post cost through confirmation, use exit at confirmation save (or some other kind of development) and post manual journal entry against service order with fixed cost...
View ArticleRe: Once-only cost posting for labour
Ignore my earlier post. Try this - 1. Create new formula with just parameter SAP_55 in calculation. 2. Then in the work center costing tab go to the Formula Constants and assign value to parameter...
View ArticleRe: Task list in plant maintenance
Greetings Karthikeyan, The tables are PLKO for the Header level (PLKO-KTEXT) and PLPO for Operation level (PLPO-LTXA1)
View ArticleRe: Task list in plant maintenance
I misread the question as Task list description instead of Operation Description in Task List. As Mr. Sebastian mentioned, you can use PLPO for operation description.
View Articleorder/PR price integration process flawed?
1) Maintenance planner creates PM work order with non-stock purchase, price/vendor unknown2) PR is generated. Buyer proceeds to source the part, create info record, update price/vendor3) Planner...
View ArticleRe: How/Where to record quantity (unit of measurement EACH) in PM work order...
In Scheduling tab of Work Center, you have the option of maintaining Work Unit under Dimension & Unit of Measure of work. It may be helpful to define UoM based on work center. I have not tried this...
View ArticleRe: Once-only cost posting for labour
I checked with confirmation and it did not work for actual cost as you had mentioned. I will try for some other approach. Aaditya
View ArticleRe: How/Where to record quantity (unit of measurement EACH) in PM work order...
We tried, but found no luck.Any other ideas?
View ArticleRe: How/Where to record quantity (unit of measurement EACH) in PM work order...
Ok - so you have to have a TIME dimension when entering UoMs in operations. So a common work-around is to create a new UoM (say ZEA, or ZKM) and give it a time dimension (say hours). You can now use...
View ArticleRe: order/PR price integration process flawed?
When you go for External operation, price will be transferred from PM order to PR & subsequently to PO. There is no reverse.
View ArticleRe: How/Where to record quantity (unit of measurement EACH) in PM work order...
He wants to make it automatic based on work center. But it is not getting supported with the solution provided.
View ArticleFunctional location
Hi expert, Now we are reflecting cost center From function location to equipment now we need manually input cost center in quipment because we are doing location wise costing in our organization....
View ArticleRe: Difference between Sub-Equipment & Equipment BOM
Hi, Sub-equipment represents a hierarchical equipment structureif you want to represent your equipment as complex structure, the whole equipment is represented as Superior Equipment under which each...
View ArticleRe: Functional location
Hi Mathew, you can manually change cost center in the Organization tab of Equipment master in IE02 even it is determined from Functional location regards,santosh
View ArticleRe: Number of times each maintenance activity type (inspection, breakdown,...
He is also mentioned that he is not looking for Activity type by which cost will be calculated. But I couldn't find any other activity type at operation level.
View ArticleRe: User Authorization for IE4N transaction
If you can update the solution by which you achieved your requirement, it will be helpful for me as well as for others.
View ArticleRe: Functional location
There are some fields which will be derived from Superior Object (Functional Location / Equipment). But if you have mentioned those while creating your Equipment, then I hope, it wouldn't have been...
View ArticleRe: Difference between Sub-Equipment & Equipment BOM
Some sub part of the equipments won't be maintained with stock. For these sub parts, business may want only Maintenance history, they may not require stock count. In this case, Sub Equipments will be...
View ArticleRe: Number of times each maintenance activity type (inspection, breakdown,...
Your demand aren´t is attended by std PM Module.When SAP developed EHP´x the idea was put FL and EQ into operation for scenary of Linear Asset Management (rounds).Best practices indicates: in principle...
View Article