Dear SAP Expert and Guru,
I have created a plan through IP41 with cycle start date on 18 April 2013, I have maintain 1 Day at the Cycle/Unit, the call horizon as 100% and scheduling period as 1 week. the Completion Requirement field is unchecked and the order type as preventive maintenance order.
After the Maintenance Plan is created, the plan is being scheduled at IP10, with the cycle start date on 18 April 2013 also. After released the first item, the scheduling was saved.
Then the the plan is being run in background through IP30 with the interval for call objects set as 1 Day, before it is being executed.
The first maintenance order is created on 18 April 2013 and the second maintenance order is create on 19 April 2013. However when come to 20 April 2013 and 21 April 2013, no maintenance order is created.
Would like to seek for the advise from the SAP guru and experts, what has gone wrong with the maintenance plan setup, that cause no creation of Maintenance Order on 20 April and 21 April 2013 and onwards.
Thank you
Regards
Leonard Tan