Re: Changing Scheduled Dates & Time for PM Order

$
0
0

In Operations details screen under Dates tab, give Must start on date as per your requirement. Also give relationship between the order operations (if you have operations in single PM Order) & then try the scheduling feature.

 

I am not sure this is what you looking for. Else please give some more details to understand your question better.

 

Also make settings in OPU7 as Do Not adjust Basic dates & dependent requirements date as operation date.