Re: Basic Start & Finshed Dates changed due to Factory Calenday - How can you Bypass the Factory Calendar

$
0
0

Greetings Darrin,

 

I understand that you have:

 

Factory Calendar A which has the special rules

Factory Calendar B which has no special rules

Factory Calendar B is assigned to the Capacity of the Responsible Work Centre of the Order

When you create an Order, it seems to be scheduled according to calendar A, while it should be B

 

Is the above correct?

 

Are you using Intervals and Shifts for your Work Centre?

 

Do you have the business function LOG_EAM_CI_1 enabled? You could then see and manipulate the Factory Calendar used for scheduling on the Maintenance Order header level?


Also, are you using Maitnenance Plans to generate your Orders and if so, which Factory Calendar is maintained on the Maintenance Plans or Strategies, if applicable?


Lastly, are you absolutely certain there are no developments to influence this in the user exits?:

IWO10012  Maintenance order: Priority handling on central header

IWO10022  Determine calendar from user exit