I will likely attempt this later in the week. Before I do, I wanted to run scheduling one more time with the old data. Before I ran it, I check the Completion Requirement flag and deleted the old order planned for 6/29. Look at screenshot below.
1) An order was scheduled for 6/23 but not for 6/30. Why is this the case? I thought completion requirement flag means that the 6/23 order would only be generated when the 6/19 order is confirmed?
2) Why is the next planned counter for 6/23 set at 687 (564+123)? Why does not the logic of the prior scheduling run prevail, meaning that the call would be at 1128? (But yet the 6/30 scheduled hold is 564 added to the prior 687 planned counter.
And for my understanding of how system works:
3) Per your recent reply, is there any difference if I enter measuring document via IK11 (after confirmation) instead of during IW42 confirmation?
4) If I make IP02 settings changes like updating annual estimate or doing the confirmation requirement flag, do I need to 'restart' the plan or do anything special for changes to take effect, or is running IP30 sufficient?