There are many things that affect the order scheduling:
- IMG setting - scheduling parameters
- Work centre settings
- Operation values e.g. work, duration, operation control key settings
- Calendars
- Etc
So one possible interpretation of the above data is that the initial order operations have no work assigned, or the operation control keys don't require scheduling, or the work centres arn't set up correctly.
Then you add a new operation which does appear to work.
Please supply a screen-shot of the operation tab.
PeteA