Re: Call horizon is transfered as 100% to the Maintenance Plan

$
0
0

Hi all,

 

I did not see you have answered already. Sorry for the delay.

 

Here are the screenshots:

 

IP11.png

This is how it creates the plan, as you can see, the call horizon is set to 100% instead of 85%. I did some further testing and this is only happening with the Call horizon. If I have values for the other parameters in my strategy, all are transferred correctly, except for this one.

IP02 - PLANNING.png

IP02 ADD DATA.pngSU3 PARAMETERS.png

Before doing the scheduling, I manually changed the call horizon from 100% to 85%. I also defined a scheduling period of 365 days.IP10.png

Thanks for your help!

KR,

 

Ximena