Thanks for the answers. Performed several simulations considering the answers but still not getting the expected result.
First Case:
Created one "Multiple Counter Plan" considering two "cycle set seq"
In the first cycle defined as 500 hs.
In the second cycle defined as 125 hs.
Initially worked perfectly. My problem occurred when generating orders inspection due to the closing of the first. If I mark the option "completion requiriment" the system only generates the order of inspection (125 hours) if the first has been completed and the next preventive 500 hs only when I complete the order of 125 hours. We need this control is independent between 500 and 125 hours.
Second Case:
Strategy - Based Plan - Suggestion of Mr. Sebastian Lenartowicz.
Good suggestion, but I also have the same problem of "completion requiriment".
Regards
Gtv.