PM-03 control key .

$
0
0

Dear All,

 

I created one maintenance order by giving the control key " PM03" and in the back ground PR is created and i converted that PR to PO and i completed the service entry sheet things also.

 

Now when i am trying to teco the order it is showing an error " Confirmation need to be done for this order" this is because of one customer exist and i know that it is mandatory to do time confirmation before technical completion of order.

 

so i am trying to confirm the order through IW41 it is showing an error " No Open item exist for confirmation" by  giving the order in the time confirmation  initial screen.

 

But when i gave the confirmation number instead of order number system is allowing for time confirmation.

 

"Could anybody explain me what exactly the logic behind this standard functionality".

 

Regards,

Harsha.